COVID-19 Management Plan – Update

We have been closely monitoring the escalation of community isolation directives by the Tasmanian Government and in response we have implemented further changes to our onsite work practices. Most notable has been changes to the makeup of our onsite construction crew....

read more

April Construction Update

Granville Harbour Wind Farm is now sending around 29 MW of renewable energy to Tasmania’s electricity grid. That’s enough clean energy to power over 10,000 homes! Our construction team is making great progress on site with 16 of 31 wind turbines completed by the end...

read more

Covid-19 Management Plan

Like many in the community, we are very concerned with the potential spread of COVID-19 Coronavirus and the potential for serious impact to the health of our workforce and their families. Over recent weeks, we have implemented significant measures to prevent the...

read more

March Construction Update

The team onsite has made significant progress over the past month, with 100% of wind turbine foundations now complete and ten wind turbines installed by the end of February. Energy Minister Guy Barnett visited the wind farm site in late February to mark the start of...

read more

First generation for Granville Harbour Wind Farm

Clean, renewable energy has begun flowing from the $280 million Granville Harbour Wind Farm on the West Coast, following the successful installation of nine of the site’s 31 advanced-technology turbines. When complete, the Granville Harbour Wind Farm will provide a...

read more

Wind farm experience for west coast students

Sixteen Year 9 and 10 students from the Mountain Heights School in Queenstown have been given a rare insight into the construction of the Granville Harbour Wind Farm this week, as part of a two-day intensive program aimed at exploring ‘future work’ opportunities in...

read more

February Construction Update

The construction of Granville Harbour Wind Farm is progressing well with 90% of wind turbine foundations now complete and several turbines now installed on site. Trenching is now underway to install the cable that connects each wind turbine to the wind farm...

read more

Community Grants recipients announced

Ten local projects will receive a share in $20K grant funding in the first year of the Granville Harbour Wind Farm Community Grants Program. Project Director Lyndon Frearson said they received a fantastic response to the call for applications with a significant number...

read more

First turbine installed at Granville Harbour Wind Farm

After almost ten years in the making, the first wind turbine has been successfully installed at the Granville Harbour Wind Farm site near Zeehan, marking a significant achievement for the project team. Workers on site were thrilled to see the first wind turbine...

read more

Wind Farm transmission line now complete

Construction workers for the $280m Granville Harbour Wind Farm have successfully completed the project's new 11-kilometre 220kV transmission line and switching station, in preparation for sending an additional 112MW of clean, zero emissions energy into the grid. When...

read more