by Admin | Jun 25, 2020 | Uncategorized
Four community-led Emergency Services Units have secured a share of $20,000 through the Granville Harbour Wind Farm Volunteer Emergency Services Grant. Project Director for the Granville Harbour Wind Farm, Lyndon Frearson, said funds would help each of the four...
by Admin | Jun 4, 2020 | Uncategorized
Our onsite construction team has made great progress over the past month, with 29 out of 31 turbines now installed, and the wind farm currently sending over 80MW of clean, renewable electricity to Tasmania’s electricity grid. Testing and commissioning work continues...
by Admin | May 11, 2020 | Uncategorized
Overall, construction of the wind farm is progressing well with 21 of 31 wind turbines installed at the end of April. Trenching works to lay underground cable are now complete and the Operations and Maintenance building is on track to be completed in May. Testing and...
by Admin | May 6, 2020 | Uncategorized
At a time when Emergency Services are again on the front line of safeguarding the community, Granville Harbour Wind Farm has announced a new Grant Program – to recognise the vital assistance emergency services volunteers and personnel provide to the West Coast...
by Admin | May 1, 2020 | Uncategorized
Granville Harbour Wind Farm has taken delivery of its final massive wind turbine tower section, marking the end of the project’s 18-week transport program. In what was the largest transportation program ever seen on the West Coast, a total of 372 oversize items –...