The first wind turbine tower sections were successfully installed during October, with the three lower tower sections for three wind turbines now erected and standing 48.6m above ground level. When complete each tower will be 137-metres high.

Our first complete wind turbine is expected to be installed by mid-November and the wind farm is on track to generate its first electricity before Christmas 2019.

At the end of October, 13 wind turbine foundation concrete pours had been completed. The installation of steel reinforcement and the construction of hardstands continues.

Construction of the 11km, 220kV transmission line to connect the wind farm to the electricity grid is now complete. During November testing and commissioning of the transmission line will take place in readiness for the wind farm to generate its first electricity.