Overall, construction of the wind farm is progressing well with 21 of 31 wind turbines installed at the end of April.
Trenching works to lay underground cable are now complete and the Operations and Maintenance building is on track to be completed in May.
Testing and commissioning work is ongoing and we expect to be able to increase the wind farm’s electricity output to 60MW in May.
Decommissioning of plant and concrete batch plant is due to commence in May.
Site rehabilitation works are also underway and progressing well.