Granville Harbour Wind Farm is now sending around 29 MW of renewable energy to Tasmania’s electricity grid. That’s enough clean energy to power over 10,000 homes!
Our construction team is making great progress on site with 16 of 31 wind turbines completed by the end of March. Trenching works to install the cable that connects each wind turbine to the wind farm substation is ongoing and civil works for the wind farm’s Operations and Maintenance building are underway.
Wind turbine component deliveries from Burnie to site will continue throughout April.