Site teams continue to work on sediment control measures and road capping works in preparation for wet weather conditions during the winter months ahead. Excavation works for our wind turbine foundations are almost done with 30 out of 31 complete and ready for installation of steel reinforcement, conduits and structural concrete.
Construction of the transmission line is also progressing well, with work to finalise pedestals, hardstands and foundations underway in preparation for the first transmission line pole installations planned this month.